About Us

Richard Haro Drafting and Planning Services Inc. was started by Richard Haro in 1977. We Incorporated our business in 1988. Richard Haro is a graduate of the University of Santa Clara and Studied Design and Drafting under apprenticeship with Dick Finnegan Inc. Richard Haro has the additional experience of having worked as a carpenter, and along side his father in construction for 20 years. The office began as a one room, one desk operation. However, because of a commitment to the best customer service, quality designs, and accurate plans to work from, we are now a 5 person office doing about 100 jobs per year. Click the link below to visit the company webpage.

Friday, June 27, 2008

The Alum Rock Project

We have a remodel going on in Alum Rock. The demo was completed last week and some of the framing and roofing has begun. This remodel will include the garage, the living room, the bathroom, one of the bedrooms, and the laundry room. We will also be adding a porch with an overhang. I've added the floor plans for this project and a couple pics of the framing that went on this week. On a side note, we have completed the San Jose remodel and will be adding a final post for that project early next week.

Friday, June 20, 2008

The Campbell Project

Here are some updated pics of our Campbell project. As you can see the framing of the walls for the master bedroom is well under way. The complete framing normally takes 3 to 4 weeks depending on the size of the job. Once the framing is complete, the construction of the roof will begin.






Wednesday, June 11, 2008

The Campbell Project

Here are the latest pics of the "goings on" at the Campbell project, and a slideshow of the progress made so far. With the underfloor and floor insulation inspections complete, the construction of the subfloor is underway. This should be complete in the next day or so and then the framing of the bedroom will begin.



Tuesday, June 3, 2008

The Campbell Project

We have begun construction on the flooring of the master bedroom addition in Campbell. The framing has been completed and the under floor plumbing is currently being installed. This will be followed by the subflooring after the underfloor inspection is completed later this week.