Week six has come to a close and the sheet rock and stucco lath have been installed. For those who don't know, the lath is a wire mesh, almost like chicken wire, that the stucco adheres to. Below is a picture of what it looks like on a house.
Friday, February 12, 2010
Tuesday, February 2, 2010
Week 5 - Los Altos San Luis Project
This week we will finish up the insulation of the walls and then begin putting up the sheet rock. Once all the sheet rock has been installed, it will be taped and textured. Below are some pictures of what the finished framing, plumbing, electrical, and mechanical look like. You will also notice that the glass block window and skylight have been installed.
Labels:
3. Los Altos - San Luis Project
Friday, January 29, 2010
Los Altos - San Luis Project Week 4 Update
This past week we have completed all the rough framing, rough mechanical, rough electrical, and plumbing. The rough all inspection was done today, so its time to move on to insullation and then sheet rock next week.
Labels:
3. Los Altos - San Luis Project
Monday, January 11, 2010
Los Altos San Luis Project Week 2
For week two of this bathroom remodel, we wil be finishing up the framing. That includes installing the pocket door and doing the rough opening for the skylight that is to be ordered this week. Below are the plans for this remodel to give you an idea of what the finished project will be. We will follow up with a progress report at the end of this week.
Labels:
3. Los Altos - San Luis Project
Subscribe to:
Posts (Atom)








